RoI budget part 1: expenditure on waterways

When Waterways Ireland spends on capital investment in either RoI or NI, the total cost is paid by the jurisdiction in which the expenditure occurs (apart from the decision by the RoI government to pay the total cost of a canal from Lough Erne to Clones, where about half of the route lies in NI).

For current spending, Waterways Ireland gets 85% of its grant income (which is itself accounts for the vast bulk of its total income) from the RoI Department of Arts, Heritage and the Gaeltacht and the balance from the NI Department of Culture, Arts and Leisure.

The RoI government expenditure plans were announced on Monday 5 December 2011. The Comprehensive Expenditure Report 2012–2014 section on the Department of Arts, Heritage and the Gaeltacht mentions waterways, or matters affecting them, in several places.

Key Outcomes of the Comprehensive Review of Expenditure

As I noted here, waterways are the lowesst priority within the department. It intends to focus on eight activities, and Waterways Ireland and An Foras Teanga are covered in the final point:

  • supporting Waterways Ireland and An Foras Teanga within the context of the implementation of the Good Friday/ St Andrew’s Agreements.

An Foras Teanga covers Foras na Gaeilge and Tha Boord o Ulster-Scotch/The Ulster Scots Agency.

Expenditure and Numbers Ceilings

No mention of waterways, but the department says that steps to be taken in 2012 will save €6 million in each year of 2012, 2013 and 2014, with further savings of €10 million to be made in 2013 and €22 million in 2014. The department’s “total allocations for gross current expenditure” are to be reduced from €232 million in 2012 to €218 million in 2013 and €205 million in 2014. I can’t quite make the numbers match, but never mind.

Estimates 2012: summary of measures

The measures are summarised under five headings, one of which — North-South Co-operation — covers Waterways Ireland and An Foras Teanga. The department expects to save €2.2 million here, but says:

Any savings, in excess of the agreed 3% per annum efficiency savings, for the North/South Implementation Bodies will require the approval of the North/South Ministerial Council. It is envisaged that savings will be achieved through efficiencies and a focus on front-line services.

The 2011 estimate for current expenditure for WI and AFT was €40 982 000; a cut of €2.2 million is about 5.4% of that amount.

Indicative savings areas 2013–2014 to remain within Expenditure Ceilings

This section shows €1 million more saved in each of 2013 and 2014 but says:

Savings, in excess of the agreed 3% per annum efficiency savings,  for the North/South Implementation Bodies will require the approval of the North/South Ministerial Council.

It is not clear whether, in the figures for 2012 and in those for 2013 and 2014, the amounts of €2.2 million, €1 million and €1 million are to be in addition to the “3% per annum efficiency savings” or whether the amounts shown include the 3%.

The introduction to the section on Indicative Savings Areas says:

Reducing overall expenditure in 2013-2014, as required by the expenditure ceilings, will be a significant challenge and require ongoing critical analysis by the Department. The Department’s funding is largely focused on supports to sustain the arts and our cultural institutions, to protect our natural and built heritage and to promote our native language. However, much of this current expenditure is also of strategic importance in sustaining and growing cultural tourism and is making a significant contribution to economic recovery and enhancing our national reputation. All areas of spending will be subject to continued evaluation to ensure that scarce resources are directed towards areas of greatest impact and value-for-money.

This is standard civil service please-spare-our-budget stuff.

2012 Estimates for Supply Services

This section no longer provides a breakdown between An Foras Teanga and Waterways Ireland. In the 2011 Estimates, AFT got roughly 40% and WI roughly 60% of the money for current expenditure; AFT required no capital funding so WI got the whole lot under that heading. I will assume that the same ratios apply for 2012 but, if anyone knows better, I will be happy to amend this.

Current spending (WI)

2010 Estimates: €25 585 000

2011 Estimates: € 24 335 000

2012 Estimates: €22 929 600 (60% of €38 216 000)

Capital spending (WI)

2008 Estimates: €11 000 000

2009 Estimates: €10 300 000

2010 Estimates: €8 000 000

2011 Estimates: €6 000 000 (or €6 002 000)

2012 Estimates: €4 500 000 (or €4 502 000) (100%)

A footnote says that the allocations to northsouthery are subject to the approval of the North–South Ministerial Council.

 

The Ulster Canal: the departmental view

I have received from the Department of Arts, Heritage and the Gaeltacht a statement on the funding of the Ulster Canal; I reproduce it here.

This statement seems to me to be more forthright than statements from DAHG’s predecessor department, which is something I welcome, and so I reproduce it without comment. I will, in a few days, offer some thoughts on the canal’s prospects.

Plot 8 has been NAMAed

The development of the Plot 8 site at the Grand Canal Docks, Ringsend, was to be the most valuable of three sites to be sold by Waterways Ireland, with Craggy Island hoping to use the proceeds to fund the Ulster Canal. The DDDA’s interest in Plot 8 has now passed to NAMA.

I provided background information from the Oireachtas Committee of Public Accounts here; the DDDA announcement is here but NAMA, alas, has no information at the moment.

DDDA had withdrawn permission for IWAI Dublin Branch to work on the graving docks at the site.

Progress is progressing on the Ulster Canal (it says here)

The Joint Communiqué from the last Plenary Meeting of the North/South  Ministerial Council meeting (18 November 2011) can now be read or downloaded (PDF) from the NSMC website. It has much to say about the Ulster Canal:

Progress on the Ulster Canal is progressing incrementally with the planning process ongoing.

Er … right. That’s it, then. Progress is progressing, eh? Well, I never.

We’ve now had an Inland Waterways Sectoral Meeting (12 October 2011) and a Plenary Meeting, neither of which has said anything about how (or whether) the canal to Clones is to be funded. Why not? Shouldn’t they show us the money?

 

NI Programme for Government

The Northern Ireland Executive’s Programme for Government (PDF) is available for download here. The accompanying statement to the Northern Ireland Assembly by the First Minister and deputy First Minister (MW Word .docx) is downloadable here and can also be read on the Assembly’s website here.

There is no mention of waterways or canals in either document.

NSMC

The Irish Times says that there is to be a meeting of the North-South Ministerial Council on Friday 18 November 2011, with the A5 road on the agenda. Perhaps there will be some news about how the proposed Clones Canal is to be funded.

The Ulster Canal

A modest proposal here for funding the canal.

Garlic for engineers

Information has arrived from the Department of Arts, Heritage and the Gaeltacht. I have accordingly updated my page about the Ulster Canal and the Infrastructure and Capital Investment 2012-16: Medium Term Exchequer Framework.

The Ulster Canal and the Irish economy

The Irish government has decided that it cannot afford to pay for:

  • a road in the United Kingdom
  • some railway lines in Dublin, Meath and the west
  • a prison in the countryside.

But what of the Ulster Canal? It is not explicitly mentioned in the Infrastructure and Capital Investment 2012-16: Medium Term Exchequer Framework document published on 10 November 2011. It is not clear that the Department of Arts, Heritage and the Gaeltacht will have enough money to pay for it: here is my assessment. In the absence of explicit information from the department, I would welcome information from other sources.