Tag Archives: lock

How much Dáil time …

… is wasted in asking and answering questions over and over again? I’d have thought that Caoimhghín Ó Caoláin TD (Cavan-Monaghan, Sinn Fein) would have realised that the government has discovered neither oil nor a crock of gold and that there is no money for a canal to Clones. The task of finding some is to be delegated to an “inter-agency group”, poor dears. I’d have thought it might be better to give the job to people with experience of unconventional fund-raising; there must be some such people around.

Hey, Brendan …

… once you’ve recruited the staff for your new government economic and evaluation service, could you send a few of them round to the DAHG to examine the Clones Canal proposal?

Date

Killaloe & Ballina are having one of Waterways Ireland’s Discover Days on Sunday 29 April 2012.

Includes “visitor attractions, water activities, arts and crafts, face painting, live music, a historical walking tour, boat trips and other land and water activities”.

More info as it becomes available.

Alexey Grigoryevich Stakhanov

There has been such interest in my posting on Stakhanovite homoeroticism that I thought I would post a few close-ups of the mural. The light fittings get in the way a bit, but you can pretend that they represent the fires of passion.

 

 

 

 

The chap at the bottom of that last one may represent Diogenes addressing a meeting of the directors of the Royal Canal Company.

 

Internet search engine

Grand Canal docks, Dublin

Salthouse Dock, Liverpool

Lock 3 Skelan, Shannon–Erne Waterway

Maybe they‘ll give me loads of money for this ….

 

Up the Barrow

A new study from WI and others is mentioned here. It doesn’t seem to be available on the WI website yet, but I haven’t yet finished reading the Erne and Lough Ree/Mid-Shannon studies that are available on the same page.

I might disagree with some of the conclusions of some of these studies, but I very much welcome the fact that they are being done and that WI is developing and promoting the waterways “product”. If only I could convince it not to waste money on the Clones Canal ….

Update: WI have a press release up, with a photo of a chap who has come out in a very fetching garment.

Clones Canal update

I’ve done a precis of developments since Novemebr 2011. There is nothing much new on the page, but it may assist new seekers after truth.

I’ve also given the overview a mild update, but without making major changes to its structure.

I’ve been making three main points about the Clones Canal proposal:

  • the expected costs are understated
  • the expected benefits are overstated
  • there is no funding available.

Just in case anyone from Clones, or from the government, is looking in, I want to point out that I have been shown to be right on two of those points so far.

First, I said that the €35 million cost figure, which was widely used by the project’s proponents, was unreliable. Waterways Ireland has recently said that the cost is now expected to be €38 million + VAT, which I gather is about €45 million. So has the government reassessed the economic case? If it has, it’s not admitting it.

Second, I said that I could not see how the Irish government was going to fund the project. I wrote:

So where is the money to come from? I’ve tried asking the public bodies that should know the answer, but they won’t tell me.

The government now admits that funding was not provided and it is clear that there will be no significant funding (ie enough to pay for construction) before 2014. Incidentally, my appeal against the refusal of information is with the Office of the Information Commissioner: I don’t believe that government should be able to keep matters of funding secret, especially if potential investors might be misled.

We have no result yet that would cast light on the expected benefits, but we do know that the boat-hire business has declined drastically in recent years. If Clones is to prosper, as I hope it will, it will need development initiatives that are easier, faster, cheaper and more effective than the proposed canal.

Limerick dredging

The Limerick Post has news here.

Value for money

Regular readers will be aware that I think the proposed canal to Clones is a bad investment. I thought it might be useful to look for information about other Irish canal restorations to see what they cost and what the return on investment has been. I understand that there was a study of the Shannon–Erne Waterway, but I can’t find a copy on tinterweb (if anyone has one to lend, please get in touch).

I therefore asked Waterways Ireland about the restoration of the Royal Canal:

I would be grateful if you could tell me the cost of the restoration of the Royal Canal, the annual cost of running it and the revenue it generates.

The reply (for which I am, as always, grateful) said:

Restoration of the Royal Canal commenced in 1987.

€37m Capital Expenditure on the restoration project funded through (1) Operational Programme for Tourism 1994-1999 (2) National Development Programme 2000 – 2007 and (3) National Development Plan 2007-2013.

The Maintenance Cost for 2012 is €2.46m.

The revenue generated by the canal in 2011 is not available.

I didn’t really expect that there would be a meaningful figure for revenue. A full assessment of the benefits would cover far more than the (probably minimal) direct revenue; I think such an assessment should be done, but that’s not what really got my attention.

According to Waterways Ireland, the Main Line of the Royal is 146 km long and has 46 locks and many bridges, some of them newly built as part of the restoration. Harbours have been improved, slipways have been provided and service blocks have been built. And all of this was done for €37 million (I don’t know whether that’s in constant prices and, if so, at which year’s rates: I’ve asked a supplementary question).

A canal to Clones would be 13 km long and, according to WI’s final restoration plan [PDF], would have one double lock (staircase pair). Some dredging would be needed on the River Finn and a new canal 0.6 km long would have to be provided; the work at the Finn end would cost €8.5 million altogether. On the line as a whole, work would be required on up to 17 bridges, some major and some minor or private bridges. And there would be a cost for land acquisition, although the Updated Economic Appraisal put that at a mere £1,268,280, a very small portion of the total cost. And then there would be the pumps and pipes to take water from the Erne, pump it to Clones and let it flow back down; it is not clear whether WI would have to pay for the water. And the total cost of this lot would be €38m + VAT, which I am told is about €45 million altogether.

Now, even allowing for the facts that there had been some voluntary and FÁS scheme work on the Royal, that no land had to be acquired and that parts of the canal were in water, I still find it difficult to see how a 13 km canal with one double lock can cost more than a 146 km canal with 46 locks. I have asked WI for a comment, but perhaps readers — especially if any of them are engineers or accountants — would be able to help to explain the mystery. Maybe it’s something simple like a mistake in the figures or maybe I’m missing something about the nature of restorations …. Enlightenment welcome.

 

Killaloe bridge

More on the new bridge here with the full public notice here [PDF]. Interesting to see how many of the names of landowners are known to me.

I see on page 6 of the notice that the ESB owns two rivers, which are occupied by the ESB, Waterways Ireland, the Inland Waterways Association of Ireland and other unknown persons. There is a canal, whose owners are unknown, which is occupied by WI, IWAI and the persons unknown, as is an island. I do hope that the council will return the canal, rivers and island when they’ve built the bridge.