Tag Archives: Northern Ireland Assembly

War over waterways: Sinn Féin -v- the Free State

I reported here that, in June 2013,the North South Ministerial Council (in inland waterways format) approved, on the same day, Waterways Ireland’s business plan and budget for 2012 as well as its annual report and draft accounts for that year. In other words, it approved the budget and plan eighteen months after the start of the year to which they applied; it approved the plans for 2012 and, on the same day, approved the outcomes.

Furthermore, by November 2013, 88% of the way through 2013, it had not approved the budget for that year (I don’t know whether it has yet done so). And, as of today (22 January 2014), WI’s annual report for 2012 has not yet been published.

I wrote:

Is it possible that one minister wants to spend very much more or less on waterways than the other does? As the total current expenditure is fixed at 85%/15%, it seems to me that one side might very well come up with a figure that the other didn’t like.

Is it possible that DCAL, run by Mr Adams’s party colleague Carál Ní Chuilín, is more keen on cross-border bodies than is DAHG, run by Fine Gael minister Jimmy Deenihan? Or are both of them struggling to find savings to pay for the Clones Sheugh, or at least as a deposit for the SEUPB?

Or could it simply be that WI is having great difficulty in cutting its expenditure to fit within the limits imposed by the RoI budget?

I then sent enquiries to Waterways Ireland, the (NI) Department of Culture, Arts and Leisure (DCAL), the (RoI) Department of Arts, Heritage and the Gaeltacht and the North South Ministerial Council. From the repsonses, and from yesterday’s statement to the NI Assembly by Carál Ní Chuilín MLA, NI Minister of Culture, Arts and Leisure, it is clear that I was right in my first para; it is possible that the first sentence of the second para is right too.

There is a major disagreement between the northern and southern departments about the level of cuts to be applied to Waterways Ireland’s budget and it is not clear what mechanism can be used to resolve it. DAHG, applying Irish government policy, wants bigger cuts than DCAL does.

NSMC

After each North South meeting, the secretariat issues a rather bland communiqué; the inland waterways ones are here. I suppose that the secretariat can’t be expected to write “There was a blazing row at yesterday’s meeting, skin and hair flying, and the ministers aren’t speaking to each other”. I mean, they wouldn’t write that even if it were true, which I’m sure it isn’t.

On 9 December 2013 I wrote to NSMC (I omit salutations and irrelevancies here):

Are you able to say anything about why the NSMC Inland Waterways did not approve the 2012 business plan and budget for Waterways Ireland until eighteen months after the start of the year in question? As far as I can see from the minutes for meetings since 2007, that is a highly unusual degree of lateness.

NSMC replied on 11 December (with a copy to the RoI Department of Foreign Affairs):

[…] this is an issue for both Sponsor Departments and they can be contacted directly.

On the same day I asked:

Have you any responsibility for seeing that the terms of the WI Financial Memorandum [PDF] are observed? It seems to me that they have been ignored in this case.

Despite a reminder, I have not yet received a reply.

DCAL

I wrote to DCAL on 10 December 2013:

I would be grateful if you could help me to understand why the North/South Ministerial Council did not approve the 2012 budget and business plan until 18 months after the start of the year to which it applied.

DCAL responded on 11 December 2013:

Waterways Ireland had submitted a draft 2012 Business Plan detailing the activities required to achieve goals set out in their 2011/2013 Corporate Plan. Recognising the challenges presented by the economic climate there were extended negotiations to agree the 2012 budget. The DCAL Minister raised concerns about going beyond the required savings advised by both Finance Departments. Minister Ní Chuilín therefore sought, and received, assurances from Waterways Ireland that frontline services would be maintained.

I sent follow-up queries on 16 December:

I am not entirely clear on the implications of your third sentence: “The DCAL Minister raised concerns about going beyond the required savings advised by both Finance Departments.”

Do you mean that Waterways Ireland proposed to cut its spending by more than the percentage cuts suggested by the Finance Departments? Or to spend less than it received (or expected to receive), in euro, from the two sponsor departments? If so, why did WI want to do that?

I would also be grateful if you could tell me what WI’s “frontline services” are and why they are deemed to be more important than other services.

And I would be grateful for more information on the reason for the extended delay in approving the busiess plan and budget: eighteen months after the start of the year, which was presumably even longer after the plan was drafted. I would be surprised to find that seeking and receiving assurances took eighteen months.

Did the delay result in a breach of the terms set out in the Financial Memorandum governing WI’s affairs?

I would also be grateful if you could tell me what delayed the approval of WI’s 2013 budget. I note from the NSMC minutes that it was not approved in June 2013; the matter is not mentioned in the minutes of the November 2013 meeting but, on 19 November 2013, the RoI Minister for Public Expenditure and Reform replied to a written question from Gerry Adams TD saying, inter alia, that “The 2013 Budget allocation to the Body are subject to on-going discussion by the two Sponsor Departments.”

That suggests that approval of the 2013 budget is at least eleven months late. I note too that the 2014 business plan and budget, and the Corporate Plan 2014-2016, were not approved at the November NSMC meeting. And I note that An Foras Teanga [Foras na Gaeilge + Tha Boord o Ulstèr-Scotch], the other North-South body sponsored by your department and the Department of Arts, Heritage and the Gaeltacht, was also, in November, awaiting approval of its 2013 budget.

There are two further items on which I would be grateful for information:

(a) is it proposed that the Hutton recommendations be applied to Waterways Ireland (and other bodies in the North-South pension scheme)? If so, what is the expected effect on WI’s budget and on staff take-home pay?

(b) WI’s accounts for 2011 (the latest I have seen) suggest that your department paid less than 15% of the money WI received from its sponsor departments. Did your department pay 15% in 2012 and 2013 and will it do so in 2014? And how do you take account of the effect of currency fluctuations on WI’s income denominated in its working currency, the euro?

Despite a reminder, I have as yet received no reply.

DAHG

I wrote to DAHG on 26 November 2013 with several questions; I include below only that relevant to this posting.

On 19 November 2013, in a written answer to Gerry Adams, Jimmy Deenihan said […]: “The 2013 and 2014 Budget allocations to the Bodies are subject to ongoing discussion by the two Sponsor Departments and will require, of course, formal approval by the NSMC.”

I would be grateful if you could tell me (a) why Waterways Ireland’s budget had not been finalised when 88% of the year had passed and (b) how that affected budgetary management in the Body.

The department replied on 3 December 2013:

As you are aware, Waterways Ireland is co funded by the Department of Arts, Heritage and the Gaeltacht and the Department of Culture, Arts and Leisure, Northern Ireland.   The 2013 Business Plan and budgets have been discussed by Ministers at NSMC Inland waterways meetings and key priorities for 2013 identified.  Indicative budgets have been provided by the Departments to Waterways Ireland as a pragmatic measure for business planning and operational purposes and the body is operating within these indicative allocations.

On 9 December I replied:

Thank you. That answers my question (b) pretty well. However, you haven’t answered (a): why Waterways Ireland’s budget had not been finalised when 88% of the year had passed.

I would be grateful for information on the causes of this extraordinary delay.

I have been wondering whether the problems of WI’s budget were very difficult to resolve or whether there was some major disagreement between the northern and southern ministers. If there was such a major disagreement, what was it about?

The department replied on 17 December 2013:

The Departments are still in discussions to agree the budgets.  The position is The Department of Culture, Arts and Leisure in Northern Ireland is not prepared to agree a 2013 budget for the Body in excess of a minimum efficiency saving of 3% set out in the two Departments of Finance Funding Framework for the North South Bodies. As you are aware from the Parliamentary Question Reply this Department’s REV provision for Waterways Ireland for 2013 is €25.463m, a 6% efficiency saving on 2012. Given the pressures on the public finances and on the Departments budget allocation, the Department is not in a position to provide any additional funding that would maintain the proportionality of funding. 85% of current funding is provided by Department of Arts, Heritage and the Gaeltacht and 15% by Department of Culture,  Arts and Leisure, Northern Ireland.

I responded on 18 December 2013:

[…] Just to make sure I understand you properly: when you say “a 2013 budget for the Body in excess of a minimum efficiency saving of 3%” am I right to presume that the phrase “in excess” applies to the savings or cuts rather than to the budget itself?

I also asked three questions about items of background information relevant to this topic:

1. I am less familiar with the NI Executive’s budgetary process than perhaps I should be. I gather that there are multi-year budgets, linked to a programme for government, with annual estimates and possibly supplementary estimates. The multi-year element seems to be stronger than in Irish budgets, but I wonder whether (aside altogether from the current economic situation) it is difficult to make decisions within the constraints of the different budgetary timescales.

2. I have not yet checked all Waterways Ireland annual reports, but reading that for 2011 suggests that DCAL paid slightly under 14%, rather than 15%, of WI’s current expenditure. Are minor deviations from the 85/15 ratio unavoidable? Do they balance over time?

3. Do currency fluctuations affect the amounts actually paid by the two departments? If so, how are the effects taken into account?

I have not yet received a reply.

Waterways Ireland

On 6 January 2014 I wrote to WI:

I would be grateful if you could tell me the effect on Waterways Ireland of the continuing dispute between its sponsor departments over WI’s budgets and business plans.

On 8 January WI said:

Waterways Ireland enjoys a supportive and positive relationship with both departments.

On 14 January I said:

I am very glad to hear it, but I don’t recall asking a question about that.

I repeated my original question, to which I have not had a reply. As with NSMC, I don’t really expect WI to be able to say anything undiplomatic. However, I would have thought that there must be some inconvenience in working to “indicative allocations”. I wonder whether they are based on DCAL’s preferred level of cuts, DAHG’s preferred level or some compromise. And if compromise is possible on the indicative allocations, why can’t the main issue be sorted out?

Furthermore, the delay in publishing the 2012 accounts suggests that there has been some real difficulty in operating under the indicative allocations regime. Or perhaps there is some other row altogether.

NI Assembly

Reporting yesterday to the NI Assembly on the November NSMC meeting, the NI Minister confirmed that there was disagreement.

Karen McKevitt [SLDP, South Down]: […] The chief executive set out a strategic direction for Waterways Ireland for 2014-16. In that, she mentioned budget efficiencies. Can the Minister highlight to the House what those might be?

Carál Ní Chuilín [SF, Belfast North]: The Member is right: the new chief executive gave us a very good and detailed presentation. Indeed, the Member will be aware — if she is not, she will be when I finish my answer to her question — that there have been additional pressures on everybody across the board in achieving efficiencies. However, as I have repeated to the Member and to other Members, and despite the meetings that I have had with Minister Deenihan around any proposed additional efficiencies that the Irish Government are saying are required, I am totally reluctant to go above and beyond any efficiencies that we agreed previously, and I have stated that to the chief executive of Waterways Ireland. That is the position. Following that, the Finance Departments and, indeed, officials and Ministers will hopefully be submitting additional or new budget plans very soon. I think that issues relating to any agreement to additional efficiencies lie beneath the Member’s question, but I can categorically state that I have not agreed to those.

“Efficiencies”, by the way, means “cuts”.

The importance of waterways to Sinn Féin

I have remarked several times here that Sinn Féin asks many Dáil questions about waterways, notably the Clones Sheugh, with Maureen O’Sullivan providing recent competition. I wrote elsewhere recently:

Waterways Ireland is a political creation: its very existence reflects a nationalist and republican desire to show the benefits of all-Ireland institutions — and a unionist desire to confine such institutions to areas of minor importance. […]

In prosperous times, managing recreational waterways is a feelgood activity, combining opportunities for local and national politicians to get their photos in the papers with relatively low risk of political controversy. Nonetheless, WI had to tread warily, especially in its early years; it has almost (but not quite) entirely avoided such controversy.

Timing

I don’t know if there is ever a good time for disputes between your paymasters, but it’s not as if Waterways Ireland, and its new CEO, didn’t already have enough to worry about. To quote again from the same piece:

Compared with British Waterways and C&RT, Waterways Ireland has very little real property from which it might derive an income — and very few other sources of income. According to its accounts for 2011 (the latest available), its total income was over £38 million but it earned less than half a million pounds from licences, property, interest, operating income (including charges to waterways users) and other sources. The rest came from its two sponsor departments.

Charges to boaters have traditionally been low or non-existent: zero for a boat kept on the Erne or on one of the Shannon lakes, with modest charges for passing through Shannon or Shannon–Erne Waterway locks; on the Grand, Royal and Barrow, an annual charge of €128 covered lock passages and mooring. There was no licence fee. Waterways Ireland has begun to impose slightly higher larger charges but may meet resistance.

But there is no immediate prospect of imposing charges high enough to make a significant difference to Waterways Ireland’s budget. That budget is set by the North South Ministerial Council: each government pays for capital works (eg harbour improvements) carried out in its own jurisdiction, while the running costs are paid in a ratio intended to reflect the proportion of the waterways in each: 15% by the Northern Ireland Executive and 85% by the republic’s Government.

Some difficulty may be caused by different timings of the budgetary processes in the two jurisdictions, but a greater problem is that the fixed ratio can lead to deadlock. WI’s budget for 2012 was not set until July 2013, eighteen months late: its budget, business plan, annual report and draft accounts for 2012 were all set on the same day. Final accounts for 2012 had not been published and WI’s budget for 2013 had not been agreed by December 2013.

The cause of the delay was that the republic’s government wanted to cut the budget by more than the Northern Ireland Executive did. The Irish economy has had severe problems in recent years and the government was unable to honour its undertaking to pay for the restoration of the Ulster Canal from Lough Erne to Clones (a short stretch that crosses the border several times). Public expenditure has been cut for all government departments and public bodies but the scale of the cuts is larger than the Northern Ireland minister wants to see. If the republic’s government gets its way, by 2016 WI’s budget will be one third lower than it was in 2010.

That is not the only financial problem that WI faces. Staff transferred to it from Irish government departments carried with them their entitlements to pensions of half of final salary plus retirement lump sums of one and a half times final salary. And, as is the norm in the civil service, the pension system was unfunded. WI had quite a few staff in their fifties and, as they now retire, their pensions and lump sums have to be met out of WI’s normal income from its sponsor departments. The pace of retirement may even by accelerated by a desire to avoid charges arising from the Hutton pension proposals.

During the era of the Celtic Tiger, Waterways Ireland prospered: it acquired much new equipment, built new offices and developed and improved facilities for boaters and other users. It now faces a much more difficult financial future and it is hard to see how it can avoid reducing its level of service. At the same time, its new CEO is — rightly — determined to continue widening the appeal of the Irish waterways to more types of users: walkers, cyclists, anglers, canoeists and others.

Maybe the two ministers might get their act together.

I will report later on other items covered in Ms Ní Chuilín’s statement; the bad (if unsurprising) news is that she is still stuck on the sheugh, but perhaps she can persuade the Imperial Treasury to pay for it.

Sheughery

I wonder why Sinn Féin asks questions when it does. This one [h/t KildareStreet.com] seems to have been asked at a time that the minister might have welcomed.

Sandra McLellan [SF, Cork East]:

To ask the Minister for Arts, Heritage and the Gaeltacht the position regarding the Ulster Canal restoration project; the steps that must be taken to complete the project; the indicative timeline for the completion of the project; and if he will make a statement on the matter.

Jimmy Deenihan [FG, Kerry North/West Limerick] [the third para is the interesting one]:

As the Deputy will be aware, in July 2007 the North/South Ministerial Council (NSMC) agreed to proceed with the restoration of the section of the Ulster Canal between Clones and Upper Lough Erne. The then Government agreed to cover the full capital costs of the project, which were estimated at that time to be of the order of €35m.

It was always the intention that the Ulster Canal project would be funded from the Waterways Ireland annual allocations, as agreed through the annual estimates processes in this jurisdiction, as well as the deliberations of NSMC in relation to annual budgets. It was a key consideration throughout the process that the Ulster Canal project would be supported by a significant level of projected income from the commercialisation of certain Waterways Ireland assets. However, the economic downturn has had a negative impact on those plans.

I am continuing to explore all possible options to advance this project within the current fiscal constraints. In this regard, I established an Inter-Agency Group on the Ulster Canal to explore ways to advance the project and to examine possible funding options for it, including existing funding streams and the leveraging of funding from other sources. The Inter-Agency Group last met on 9th October and will meet again next week, on 9th December.

In the meantime, the Ulster Canal project is progressing on an incremental basis. Planning approvals have now been received for the project in both jurisdictions. Compulsory Purchase Order land maps are in preparation and consideration is being given to how the construction work and other technical aspects of the project will be structured once the necessary lands have been secured. The timeline for completion of the project will be determined when these preparatory steps have been completed.

I welcome these developments, which, I am sure the Deputy will agree, are a significant milestone for the project.

Hmm. The inter-agency group first met on 20 September 2012 and its second meeting was to take place in May 2013 or thereabouts. Now it’s going much faster, with meetings on 9 October and today, 9 December. Does this suggest that the group has found a pot of gold? Is there any link to the cancellation of SEUPB funding for the Narrow Water project?

And what has been going on in (and around) the North/South Ministerial Council? At its June 2013 meeting the Council approved or noted:

  • the business plan for 2012 (which had ended six months earlier)
  • the budget for 2012
  • the annual report for 2012
  • the draft accounts for 2012.

That suggests to me that there was either a major disagreement between the northern and southern ministers or a serious problem that rendered ministers unable to approve the WI budget and business plan until 18 months after the documents were required. Could it be that the northern minister, Carál Ní Chuilín [SF], like other NI politicians, had been looking for something from the waterways sector that hasn’t been delivered so far?

Note also that Jimmy Deenihan said

[…] consideration is being given to how the construction work and other technical aspects of the project will be structured once the necessary lands have been secured.

I understand that the design and construction of the Clones Sheugh was to be put out to tender but I wonder whether keeping the work in house might help WI to meet its increasing wage costs with a declining budget.

 

 

 

No Newry is bad news

In October I wrote about a Northern Ireland Assembly debate on a proposed Newry Southern Relief Road. I said:

… the debate was remarkable for its demonstration of cross-party agreement: not so much on the desirability of public works (a desideratum of Irish politicians since the eighteenth century) as on the irrelevance of the Narrowwater bridge.

[…]

It must surely be unlikely that there will be two crossings of Carlingford or the Newry River [and canal] within a few miles of each other. But if one option, the Newry Southern Relief Road, helps to relieve Newry and Warrenpoint traffic and the other, the Narrowwater bridge, doesn’t do so, then the first option would seem to be the rational choice.

Yesterday, 12 November 2013, Martin McGuinness [SF, Mid Ulster] reported to the Northern Ireland Assembly on the recent plenary meeting of the North/South Ministerial Council. He and others expressed support for the Narrowwater project. This question is revealing:

Caitriona Ruane [SF, South Down]: Go raibh maith agat agus go raibh maith agat don LeasChéad-Aire as an ráiteas sin. I welcome the statement from the deputy First Minister. Does he agree that the Narrow Water bridge project is a very good project for everyone in the Louth/Down area, that the chambers of commerce are representing every single community — Kilkeel, Warrenpoint and Rostrevor — and that the project went through a very rigorous process in relation to the SEUPB and came out at the top of the competitive process?

She made no mention of Newry; nor did any other contributor to the debate.

 

Waterways minister keen on waterways

An exchange from the Northern Ireland Assembly on 7 October 2013, thanks to theyworkforyou.com.

Pam Brown (DUP) asked the Minister of Culture, Arts and Leisure whether inland waterways could be developed to provide a major leisure and recreational activity resource.

Carál Ní Chuilín (Sinn Féin; Minister for Culture, Arts and Leisure): Waterways Ireland is one of the all-Ireland bodies that my Department has responsibility for. You can see the value of the work that it does, particularly in rural areas. I am also working with some councils to improve some of the waterways within their control. I agree with the Member that inland waterways provide brilliant opportunities not just for tourism but for local leisure. They are the economic driver in some towns and villages.

Pam Brown (DUP): I thank the Minister for her answer. She has touched on my supplementary question. Does the Minister agree that the development of inland waterways, while a great source of leisure and recreational activities, can also act as a catalyst for urban and rural regeneration?

Carál Ní Chuilín (Sinn Féin): I agree. I made a statement to the House in July, I think, about some of the events that take place at inland waterways across the island. Those events include festivals and family fun days. Huge numbers attend those events, and they act as economic drivers. Not only are those responsible keen to make sure that they are further developed, but people from other areas visit those festivals in towns and villages to see how they can extract that product for their area. They see the potential and outcome of those events.

That’s good: nice cheap family fun days, not expensive and unnecessary waterway restorations.

Sinn Féin and the Clones Sheugh

Northern Ireland Assembly debate 6 November 2012, via TheyWorkForYou.com:

Phil Flanagan (Sinn Féin): […] Will the Minister provide an update on the restoration of the Ulster canal from Clones to Upper Lough Erne?

Martin McGuinness (Sinn Féin): As I said, there was a presentation on the issue at the North/South interparliamentary forum, and the planning processes are up and running. I understand that, on the Cavan side of the border, it has been successfully concluded. There is still some work to do on this side. Everyone realises, from a tourism point of view, that this is filled with all sorts of potential for us, particularly in the context not only of whatever construction jobs will be created by the project but of the prospects for utilising our waterways in a way that can bring employment to local communities.

For “everyone” read “everyone except irishwaterwayshistory.com and a few other sane people”.

The NI Assembly discusses waterways

The Minister of Culture, Arts and Leisure,  Carál Ní Chuilín [Sinn Féin], reported to the NI Assembly yesterday on the North/South Ministerial Council (NSMC) inland waterways meeting held in Enniskillen on 14 February 2012, which I reported on here. The minister’s statement didn’t add anything to what the NSMC minutes [PDF] said, but some interesting points came up in the discussion afterwards.

Disposals

[Karen] McKevitt [SDLP, South Down]: One of the four specific recommendations considered at the meeting was a change to the legislation for the disposal of a waterway or part of a waterway by Waterways Ireland. Why does Waterways Ireland need that power? Does it have any plans to make such disposals?

Ms Ní Chuilín: We want to give Waterways Ireland the authority to dispose of small areas of land without needing approval from both Departments. That provision will be de minimis and will cover the disposal of land that is worth less than £25,000. It will also allow for good practice and good governance, and will ensure that there is a clear understanding of what Waterways Ireland can and cannot do. The creation of such a provision has been raised before and we said that we would bring it forward. Therefore, this is progress and, through it, we are providing clarity.

This is sensible: WI shouldn’t have to bother ministers about such minor disposals.

The Clones Canal

Perhaps the penny is beginning to drop. Mr McCarthy [Kieran McCarthy, Alliance Party, Strangford] said:

I thank the Minister for her statement. The Minister said that the next NSMC waterways meeting will set out “options for advancing the Ulster Canal project.” Is there any hint that that project may be curtailed or that less will be done than was formerly envisaged?

The minister’s answer:

[…] Some time ago, the Irish Government made a statement that their budget for developing some of the capital works that they had committed to was under threat. The Ulster canal was mentioned in that statement.

At previous NSMC waterways meetings, we agreed to progress that project as much as possible. One of the first stages of the programme of work was to seek leave for planning permission, and that has happened. The project will be kept under constant review at each stage, and the Ulster canal project is firmly at the top of the agenda of NSMC waterways meetings and other meetings that I have with Minister Deenihan. Any progress on that project will be reported at the next NSMC waterways meeting in June.

The minister has shifted the focus to the planning application as the mark of progress. She did not tell Mr McCarthy that there is no money in Waterways Ireland’s budget for any substantive construction work before 2014.

Tom Elliott [Ulster Unionist Party, Fermanagh and South Tyrone] asked about costings for the whole of the Ulster Canal:

[…] She mentioned the Ulster canal and, in particular, the Clones to upper Lough Erne portion of that canal. Will she give us details of the costings of the entire Ulster canal project and, in particular, the Clones to upper Lough Erne portion, for which planning permission has now been sought? Have those costings been reviewed recently?

The minister confirmed the figure of €45 million, reported here on 16 December 2011, for the Clones Canal, but note her inclusion of the word “currently”: there might be more increases before construction could begin in 2014. She provided no information about updated figures for any canal from Clones to Lough Neagh:

The 2006 business case indicated a capital cost of £171·5 million for the restoration of the entire canal. That included site navigation, an environmental impact assessment and project management and construction costs. The estimated costs to restore the Clones to upper Lough Erne section is currently €45 million. The construction costs for that section will be entirely funded by the Irish Government, and, when it is built, my Department will contribute ongoing operational costs that are estimated at £37,000 per annum.

If the same 29% increase were applied to the rest of the canal, the total cost would be £220.5 million, just under €350 million.

Tha Boord o Watterweys Airlann

The other discussion of interest was about the proposal to have a board for Waterways Ireland. Robin Swann [Ulster Unionist Party, North Antrim] asked:

Can the Minister provide clarification on the option to set up a board that comprises fewer than 12 members to present proposals for consideration at a future NSMC meeting on inland waterways? Would that not be the establishment of a further North/South quango to advise the North/South Ministerial Council? If that board is established, what would it discuss, who would decide its remit, and who would be on it?

The minister replied:

[…] In my statement, I said that proposals are being brought forward on the board. Waterways Ireland is the largest of the North/South bodies, yet it does not have a board. Bringing forward proposals for a board does not suggest that there are any issues. However, for the largest body not to have a board is not in keeping with good practice in governance. To that end, it will have a board. Proposals for it will be brought forward at the next NSMC meeting. I am happy to share the outcome of that meeting with Mr Swann, other members of the Committee for Culture, Arts and Leisure and, indeed, other Members.

And Jim Allister [Traditional Unionist Voice, North Antrim] asked:

[…] Is that for an advisory board or a management board? Given that Waterways Ireland has been running for many years without a board, why is it now thought necessary, or is it just jobs for the boys that will add to the expense of Waterways Ireland?

The minister replied:

I am sure that the Member heard the answer that I gave to Robin Swann about setting up a board. One of the recommendations of the St Andrews review report was that a 12-person executive management board be appointed to direct Waterways Ireland’s affairs. Waterways Ireland is the biggest of the North/South bodies with no board; therefore, it is in keeping with good policy, practice and governance that options and proposals to establish a board will be brought to the next NSMC meeting.

The minister is quite right: there should be a board.

 

 

 

Inland fisheries

There was an important debate in the Northern Ireland Assembly on this subject yesterday. While the salmon received much of the attention, the state of the Lough Neagh eel fishery was also discussed.

UC@NIA

The Northern Ireland Assembly mentioned the Ulster Canal twice on 20 February 2012; the Lagan was mentioned too. Nothing new, really.

Northern subsidy?

The Waterways Ireland Corporate Plan 2011–2013 [PDF] tells us how the body is funded:

Waterways Ireland receives grants from money voted by the Northern Ireland Assembly and the Houses of the Oireachtas. At present 15% of recurrent or maintenance funding is provided by the Assembly in Northern Ireland and 85% by the Irish Government reflecting the current distribution of the navigable waterways, while capital development works carried out by Waterways Ireland are funded separately by the jurisdiction where the works are carried out.

This is not new information; I quote it here only for convenience (but note how “the Houses of the Oireachtas” becomes “the Irish Government”).

Now look at these figures from Annex C of the Corporate Plan. They show, for 2011, the proposed budget for current expenditure on each waterway. I have rearranged them in descending order of amount:

  • Grand Canal €4,559,160
  • Shannon Navigation €4,240,398
  • Royal Canal €2,713,052
  • Barrow Navigation €1,296,538
  • Shannon–Erne Waterway €1,269,450
  • Erne System €380,239
  • Lower Bann €375,270.

It would be interesting to compare the value for money offered by each waterway. However, it would be necessary to allow for the non-navigational responsibilities WI has for each waterway: for example, it has to look after a lot more bridges on the Grand Canal than it does on the Erne. I do not have enough information to make valid comparisons.

My immediate interest is in the figures for the Erne and the Lower Bann. Granted, the burdens on WI are in some respects lower than for other waterways. But the two northern waterways are getting a total of €755,509 spent on them out of a waterways total of €14,834,107, which is about 5%. Yet the NI Assembly is paying 15% of WI’s current expenditure.

Perhaps I’m missing something. I would welcome enlightenment.

 

A slight delay

Keeping up with Waterways Ireland’s corporate publications is a bit of a chore: there doesn’t seem to be any system allowing interested citizens to sign up for alerts, so you have to troll on over to the relevant web page and check for new stuff (I’ll see whether Page2RSS works).

Anyway, I don’t know when the WI Corporate Plan 2011–2013 [PDF] was uploaded, so it may be that everybody has already read it, although it wasn’t approved until October 2011:

This Corporate Plan 2011 – 2013 was approved by the North/South Ministerial Council on 12th October 2011 subject to budgetary considerations by the Northern Ireland Assembly and the Houses of the Oireachtas.

Naturally, I had a look for mentions of the Ulster Canal. It’s still there in Business Objective 2, which includes this:

Progress restoration of the Ulster canal from Upper Lough Erne to Clones.

But what isn’t there is any money (other than small change). Annex B shows these amounts of expenditure:

  • 2011: €390,000
  • 2012: €140,000
  • 2013: €390,000

With an expected total cost of €45,000,000, it seems that there won’t be much progress in the next few years.

Thank goodness.